Warehouse: Install New Freezer
NBR: 2010-9
Title: Warehouse: Install New Freezer
Project Manager: Bryan Visscher visscher.b@mail.wsd.wednet.edu
Contract Administrator: Pamela Peer peer.p@mail.wsd.wednet.edu
Closing Date: Thu, 03/31/2011 - 3:30pm
Project Description: Install Concrete Pad and Install New Freezer Per Manufacturers Specifications
Plan Holder List: Cusick Construction, Blodgett Construction
Awarded to: Blodgett Construction $92,214.41
Status: Completed