NBR:  2012-03

Title:  Sunnyslope Elementary School Drainfield Repairs

Project Manager:  Bryan Visscher visscher.b@mail.wsd.wednet.edu

Contract Administrator: Pamela Peer peer.p@mail.wsd.wednet.edu

Closing Date:  Mon, 07/23/2012 - 3:30pm

Plan Holder List:  Allemandi Construction, Rayfield Brothers, Pipkin Construction, Hurst Construction, Smith Excavation

Awarded to:  Smith Excavation $5,350.00